WITS Activity Codes

CodeActivityDescription
0Undefined Status Anything not covered by other activity codes.
1Rig Up & Tear Down The act of installing and removing the rig. The start and end of these operations will be specified by the operator.
2Drilling The process of making new hole.
3Connection (drilling) The process of adding a joint of drillpipe to the string.
4Reaming Return to total depth with pumps on, pipe rotating and/or weight on bit.
5Hole Opening Act of opening pilot hole to full gauge.
6Coring Act of cutting a conventional core.
7Condition and/or Circulate mud Pumps on with pipe turning slowly and/or some pipe reciprocation and/or no weight on bit and no increase in total depth.
8Tripping In The act of running the drillstring into the hole.
9Tripping Out The act of pulling the drillstring from the hole.
10Lubricate Rig Regularly scheduled service or preventative maintenance which interrupts the current rig activity.
11Rig Repair An unscheduled interruption to the current rig activity resulting from equipment failure, e.g. blown pop-off valve, blown swivel packing, dropping blocks etc.
12Cut/Slip Drilling Line The act of cutting and slipping the drilling line.
13Deviation Survey The activity associated with taking a survey.
14Wireline Logs Time spent rigging up, running, and rigging down wireline tools.
15Run Casing The time from rigging up to run casing/liner until casing/liner is in position.
16Cementing The time spent on cementing operations.
17Plug Back The time spent setting a cement plug. This does not include tripping.
18Squeeze Cementing The time spent performing a cement squeeze job. This does not include tripping.
19Wait On Cement The time required for the cement to gain sufficient strength to drillout, or the time required by a regulatory agency after the cement plug is bumped. This time will be supplied by the operator.
20Drill Cement and/or Float Equipment Drilling cement, float collar and/or casing shoe following a cement job, plug back, sidetrack etc.
21Nipple Up /Nipple Down BOP Stack The act of installing or removing the BOP stack. This time will be recorded only if it exceeds the wait-on-cement time.
22Test BOP Regularly scheduled BOP test after casing, etc.
23Drill Stem Test The time spent drill stem testing. This does not include tripping the test tool.
24Fishing The time spent attempting to fish items from the hole. This does not include tripping.
25Directional Work The time spent performing directional work (not simply a survey). This does not include tripping.
26Well Control Well kill and associated operations, e.g. observe pressures, weight up mud, circulate on choke, etc.
27Stuck Pipe Act of freeing pipe which cannot be pulled by normal processes.
28Wait on Weather Waiting caused by adverse weather conditions.
29Subsea Run/Pull Riser, stack, wear bushing, etc.
30Flow Check Check for fluid flow from well while not pumping
31Pressure Integrity Test Pressure test on the casing or a "leak-off" test on exposed formation.
32Lost Circulation Time spent combatting lost circulation problems
33Short Trip In The act of running the drillstring back to bottom after a short trip.
34Short Trip Out The act of pulling the drillstring for a short trip.